Metro Reports: King Parks, Bowlero, 500 NW 23rd, and more

A building permit was issued for PCRI’s King Parks Apartments. The development will include 70 residential units, 50 of which are larger family-sized two and three bedroom units. All rental units are affordable to households at or below 60% of the area median family income (MFI), with 24 units affordable to those at or below 30% MFI.

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers January 7th to January 13th, 2019. 

SERA Architects have scheduled a Pre-Application Conference and requested Design Advice for a project at 2135 NW 29th Ave:

6-story market-rate apartment building (approx 200 units) with below-grade parking.

Early Assistance has been requested for a project at 5904 SE 89th Ave:

Construct (2) nine unit apartment buildings and (2) twelve unit apartment buildings. Complete two lot confirmations to produce four individual legal lots that will each site an apartment building.

Early Assistance has been requested by C2K Architecture for a project at SW Marquam St and Sam Jackson Rd:

Multi-Family and Senior Housing

Early Assistance has been requested for the Lloyd Center Bowlero:

Remodel/conversion of former retail space to a Bowlero bowling facility with arcade, bar and food service components. Includes facade modification and exterior signage.

A Pre-Application Conference has been scheduled by Studio 3 Architecture to discuss a project at the Southwest corner of NW 23rd and Roosevelt St:

A Pre-Application Conference to discuss construction of a 6,700 square foot, two story office building and a 3,500 square foot warehouse. Fifteen surface parking spaces are proposed with access from NW Roosevelt Street. The approval criteria for this review are found in Chapter 33.815.125 of the Portland Zoning Code.

A Pre-Application Conference has been scheduled by Studio 3 Architecture to discuss a project at 5275 N Bowdoin St:

Proposed zone change from R2.5to CM2. Remove existing home and construct a single building (20 units) for affordable housing

500 NW 23rd Avenue has been submitted for building permit review by Allied Works Architecture:

New construction of 4 story mixed use building, retail on the first floor with associated site work (tenant improvement separate)

A project at 506 NE 53rd Ave has been submitted for building permit review by Studio 3 Architecture:

Construct new 4 story (18) unit apartment building with associated site work and detached trash enclosure under 120sq ft

A building permit was issued to Merryman Barnes Architects for the King Parks apartments at 6465 NE Martin Luther King Jr Blvd:

New 4 story affordable housing apartment building with flats, 2-story townhomes and covered parking

Metro Reports: 1120 SE Madison, 7447 N Mohawk, King Parks Apartments, and more

A building permit was issued to Siteworks Design Build for alterations to a building at 1120 SE Madison

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights.

Early Assistance has been requested by Studio Coop Architecture for a project at 10246 NE Halsey St:

REMODEL EXISTING BUILDING – Remove 2 walls of existing 1 story building and develop a 2 story building with roof top space. Building will retail, restaurant and event space. Looking to meet plan district standards.

Early Assistance has been requested for a project at 8814 N Willamette Blvd:

Two 4-plex buildings (8 units) with access in rear (corner lot). No affordable housing.

Early Assistance has been requested for a project at 1445 N Hayden Island Dr:

New single story 6200 sq ft building for retail use, with 45 parking stalls on existing vacant pad. Please see 2015 EA (15-250140).

Early Assistance has been requested for a project at 2626 SE 122nd Ave:

2855 sq ft (60-seat) quick serve restaurant with drive-thru.

Early Assistance has been requested for a project at 5524 SE 82nd Ave:

Proposal is to demolish the existing structures and construct new 4,520sf mini-market and a new 2,970sf canopy over a new quick vehicle service facility with four (4) dispensers. The existing underground storage tanks will remain. New piping for petroleum products. Fueling facility will provide eight (8) vehicle fueling positions, as it does currently.

Early Assistance has been requested by Merryman Barnes Architects for the King Parks Apartments at 6445 Northeast Martin Luther King Junior Boulevard:

Follow up EA – with planner only (Jason) to confirm that this project will meet Community Design Standards. Please note – this is a PHB funded Affordable Housing Project which consists of 70 units of affordable housing (100% of project).

Early Assistance has been requested for a project at 8435 NE Glisan St:

Proposal is for developing a new academic building and would like to update its impact mitigation plan (IMP). The univeristy would like to explore its options under the existing IMP as well as the new campus institutional (CI) zoning district.

Early Assistance has been requested for a project at 13655 E Burnside St:

Looking at purchasing the northern section of this lot to build more units and possibly “connect” it with their current development on R109424. See CO 15-170799.

A project at 1944 SE Tacoma St has been submitted for Type II Design Review by Works Progress Architecture:

New construction 3-story multi-family development comprissed of (12) units. This is not affordable housing. (9) standa4rd parking spaces are provided and (31) bicycle parking spaces. Solar arrays are proposed for south facing roof slopes.

A project at 3024 SW Beaverton Hillsdale Hwy has been submitted for Type II Environmental Review:

Developing three lots with five duplexes, one tri-plex, and one four-plex. The existing single family home to remain. Also constructing a water quality facility in public ROW, which is in the “c” overlay. Please note there has been a Public Works Alternative Review for this development (see PW 16-122770).

A development at 7447 N Mohawk Ave has been submitted for building permit review by Crescent Custom Homes:

Construct new 2-story 4 unit condominium building, 2 units on main floor and 2 units on 2nd floor with 2 attached trash rooms and bike rack area, and associated site work – building 1

Construct new 2-story 4 unit condominium building, 2 units on main floor and 2 units on 2nd floor with 2 attached trash rooms and bike rack area, and associated site work – building 2

A building permit was issued to Siteworks Design Build for a project at 1120 SE Madison St:

Shell permit – addition-alteration of existing building w/ partial basement structure. Upgrade to meet ASCE41. No occupancy this permit. Buildout of common core space and second floor addition. New windows, doors, skylights, roof. Row upgrades, parking and roof deck and landscape improvements

A building permit was issued to Robert Evenson & Associates for a project at 702 SW Broadway Dr (previously 664 SW Grant):

Construct new 3 story, 5 unit apartment building, no parking, includes associated site work, sloped lot 6/7/2016 a johnson: note that plan set shows address as 644 SW Grant, which is about 1 mile from 702 sw broadway. Emailed permit-tech for clarification/correction.

A building permit was issued to Deca, Inc for a project at 15075 SE Stark St (previously 15023 SE Stark St):

New 3 story 40 unit apartment building, site improvements, stormwater facility, and 21 stall parking lot.

Weekly Roundup: The Woodlark, 1127 SW Morrison, 5 MLK, and more

Cornelius-Woodlark

Image of The Woodlark hotel, after renovation

Architect magazine released its top 50 firms of the year, with Portland-based ZGF Architects in the #1 place. Also on the list from Portland was Hacker, at #13. In the design rankings of nationwide firms Works Partnership came in at #5, ZGF at #7 and Hacker at #17.

A single story commercial building at SW 12th & Morrison is about to be demolished, reports the Portland Business Journal. The building will make way for the 1127 SW Morrison office building.

The DJC reported on how “Sellwood growth stirs residents“*. Projects planned or under construction in the neighborhood include Spokane.137119 SE Milwaukie, Galaxie Lofts and Sellwood Bridgehead.

Knot Springs Spa & Fitness has opened in the Burnside Bridgehead tower Yardaccording to the Portland Business Journal. The 11,500 sq ft facility “offers monthly memberships as well as services by appointment”.

The Oregonian reported that ‘Top Chef’ finalist Doug Adams will be opening a restaurant named Bullard in The Woodlarkthe Downtown hotel that be created in the Hotel Cornelius and Woodlark building. Existing business Johnny Sole, currently located at the site, will close according to the Portland Business Journal.

City Observatory asked if inclusionary zoning in Portland is “a good way to provide more affordable housing, or will it actually worsen the constrained housing supply that’s a big cause of higher rents?”

The Portland Business Journal wrote that the Portland Development Commission has agreed to spend a further $1 million to demolish the feed mill building at Centennial Mills. Current plans still envision the retention of the iconic flour mill.

An investigation by The Oregonian covered how Commissioner Saltzman withdrew the award of city owned land and funding for Meta Housing’s Creators Collective project, and instead gave it to Portland Community Reinvestment Initiatives Inc, for their King Parks project.

The Abigail, the latest affordable housing development in the Pearl, had a grand opening on Friday. The 155-unit apartment building includes 128 units for families making between 30 and 60 % of area median family income.

Places over Time wrote about the latest iteration of 5 MLK in “How I Learned to Stop Being and Architect and Design by Committee.”

The Foster Powell blog wrote about the 131 Units of Housing Coming to Foster at 5811 SE Boise, with more on the way at other sites.

The Portland Business Alliance endorsed the city’s affordable housing bond as an “important part of the equation to address housing affordability in Portland,” reports the Portland Business Journal.

*This article will be unlocked for the rest of this week. After this week it will only be viewable by DJC subscribers.

Metro Reports: Station Place Lot 5, 72Foster, 1500 SW Taylor, and more

Station Place Lot 5

A building permit was issued for Station Place Lot 5 by Hacker architects

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights.

SERA Architects have requested Design Advice for a project at 1500 SW Taylor St:

Design Advice Request for a Type III Design Review for the construction of a new 10-story mixed-use building with some ground-level retail and residential development, approximately 150 residential units. The project will include two-levels of below-grade parking. See parent folder (PC 16-175812).

Early Assistance has been requested by William Wilson Architects for a project at 310 SE 12th Ave:

Proposal is for new four-story 84 unit apartment building with basement.

Early Assistance has been requested by Ankrom Moisan Architects for the N Williams Center at 2156 N Williams Ave:

Demo existing buildings and develop a new 4 story 61 unit apartment building with 30 parking spaces

Early Assistance has been requested by Wright Architecture for a project at 6804 N Maryland Ave:

New 3 Story 6 unit development with property to be divided; Questions regarding feasibility.

Early Assistance has been requested by TVA Architects for a project at 1120 NW 21st Ave:

Proposal is for a new four-story 45ft tall mixed-use/multi family residential development including 46 apartments, ground floor leaseable space, ROW and site improvements, landscaping and 51 long term and 3 short term bike parking stalls. On on-site parking provided.

Early Assistance has been requested by Holst Architecture for 72Foster at 7120 SE Foster Rd:

Project consists of new 80,000 sf four story building that will include 108 affordable housing units with approx. 10,000 sf of ground floor retail space and approx. 54 parking spaces.

Early Assistance has been requested by TVA Architects for a project at 3802 NE Martin Luther King Jr Blvd :

Early Assistance with meeting to discuss proposal for a new (5-story, 57′ tall) multi-family residential development.

Early Assistance has been requested by Merryman Barnes Architects for the King Parks apartments at 6445 NE Martin Luther King Jr Blvd:

New development of a 69 unit affordable housing project with community room, orrices and service spaces on the ground floor with 24 parking spaces accessed off the alley.

Early Assistance has been requested by TVA Architects for a project at 5036 NE Sandy Blvd:

New 6 story market rate mixed-use/multi-family development. 90 units proposed with 1 floor mixed use retail, 21 car parking spaces and 139 bike parking spaces.

Early Assistance has been requested by Gerald Rembowski Architect for a project at 1125 N Schmeer Rd:

Two lot land division in order to be able to build second hotel with 76 rooms on the proposed eastern lot.

A Pre-Application Conference has been scheduled by LRS Architects and Lever Architecture for Block 45:

A Pre-Application Conference to discuss a proposal for a new twelve story building. The building is proposed to have 7,500 square feet of ground floor retail and approximately 264 residential units. Project is a mix of affordable and market rate housing. No parking is proposed.

LRS Architects have submitted NW 14th & Raleigh for Design Review:

New construction of a twelve story building with 93 units of affordable housing, associated resident amenities and a ground floor commercial space on a 10,000 sf site. Parking for 16 cars will be provided on the ground floor.

GBD Architects have submitted revisions to Oregon Square for Design Review:

Type III Design Review for a 4-block phased development. Changes to LU 15-156716 are being proposed. Phase 1 is the superblock be developed into two apartment towers around a publicly accessed ped-only plaza.

Works Partnership have applied for demolition permit and building permit for a project at 110 SE Washington St:

Demo existing 2 story warehouse

Construct new 9 story building with underground parking;

Urban Development Group have applied for a building permit for a project at 316 NE 28th Ave:

Construct new, 4 story apartment building with 74 units, below grade parking

Building permits are under review for a project at 6400 SW Canyon Ct:

Building 1 – 76 units, 4 stories of living over 2 stories of below grade parking

Building 2 – 72 units, 4 stories of living over 2 stories of structured parking

Building 3 – 59 units, 3 stories over 1 story of structured parking

Building 4 – 60 units, 3 stories of living over 1 floor of structural parking

Stack Architecture have submitted a project at N Crawford & N Charleston Ave for building permit review:

New construction apartment bldg on north side of property – see 16-185213-CO for attached plaza and apartment bldg C

New construction 4 over 1 apartment building with parking garage and plaza -see 16-185235-CO for bldgs A&B

Iselin Architects have submitted a project at 8705 SE 13th Ave for building permit review:

New 5 story 24 unit apartment building with underground parking

Bora Architects have applied for a foundation permit for Block 20:

Block 20 – Foundation permit for 21 story condo tower – This permit includes piles, pile caps, below grade utilities and slab on grade.

Building permit is under review for a project at 223 SE 146th Ave:

Construct 3 story, 3 unit apartment building

Construct 3 story, 24 unit apartment building

Construct 3 story, 24 unit apartment building, includes parking and associated site work, detached trash enclosure is less than 120ft in area

Ankrom Moisan Architects have submitted the East Burnside Apartments at 10506 E Burnside for building permit review:

New construction of five story multidwelling residential building, consisting of 52 unit with 15 tuck-under parking spaces. Interior trash room

Myhre Group Architects have submitted a project at 5025 NE 21st Ave for building permit review:

Construct new 4 story, 28 unit apartment building, no parking, includes associated site work

Urban Development Group have submitted a project at 4926 SE Division St for building permit review:

New construction of a mixeduse building consisting of 127 apartment units and 7000 sf of ground floor commercial space; below grade parking

Myhre Group Architects have submitted a project at 4901 SE Hawthorne Blvd for building permit review:

Construct new 4 story mixed use building with (46) units and 2737 sf of retail, interior trash room

The Seven Corners Community Collaborative at 1949 SE Division St has been submitted for building permit review:

Construct new 4 story office building with retail and parking on ground floor, offices on floors 2-4, includes associated site work

Building permits are under review for a project at 5414 SE Duke St:

New 2-story building with 8 guest rooms

New 2-story building with 8 guest rooms

New 2-story building with 8 guest rooms

A building permit was issued to Scott Edwards Architecture for a project at 1451 NE Alberta St:

Redevelopment of existing building to create ground floor warm shell retail and two floors – 10 units – residential units above. Including street landscaping. Separate tenant improvement permit required for occupancy of 1st floor shell space.

A partial permit for excavation and piling at Station Place Lot 5 was issued to Hacker Architects:

Partial Permit for new 8 story building, scope includes erosion control/site preparation, excavation/piling, underground utilities, entire concrete structure.

An excavation and shoring was issued to GBD Architects for the Broadway Tower:

Excavation and Shoring for new 19 story commercial high rise structure with retail, office and hotel uses and 4 floors of below grade parking

A building permit was issued for a project at 2845 NE Columbia Blvd:

Construct new 103,912 sq ft, 3 story self storage building with associated utilities, parking and landscaping.