Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers August 30th, 2021 to September 5th, 2021.
Early Assistance has been requested for a project at 2700 SE Tacoma St:
Construction of a new 4-story, self storage facility, totaling approximately 173,000 square feet. Site improvements consist of grading and associated improvements include parking, landscaping, utility improvements and buffer enhancements, across a total site area of 119,212 sf (2.74 Acres).
A Pre-Application Conference has been scheduled by William Kaven Architecture to discuss a project at 2624 SE Division St:
Five-story, 33,500 sf, 52 unit apartment project with inclusionary housing. Flow-through stormwater planter. Plan to pursue meeting Design Standards per 33.420.050 in lieu of Type II Design Review. Optional Pre-Application Conference. No land use reviews anticipated.
A Pre-Application Conference has been scheduled by Jones Architecture to discuss a project at the SW Corner of SE 6th & Alder:
A Pre-Application Conference to discuss construction of approximately 200 units of affordable housing,.Two standard B loading spaces are proposed with access from SE 6th. No on-site parking is proposed. Proposed height is 159 feet.
The new DoveLewis at 1947 NW Overton St has been submitted for a Type II Design Review:
The applicant requests Type II Design Review approval for a new three-story building with underground parking in the Town Center area of the Northwest Plan District. The project concept is a three- story building with below-grade on-site parking capacity. DoveLewis, which needs to expand, plans to occupy the first two floors. The third floor will be available for lease to one or more additional tenants. Adjustment review is included to allow on-street curbside loading in lieu of one off-street loading space Section 33.266.310.
A project at 2440 N Lombard St has been submitted for building permit review:
PDOX PS – new 16-unit apartment building and associated site work.
A selective demolition permit was issued for the Benson High School Modernization at 546 NE 12th Ave:
Benson Modernization – interior selective demo of existing building and demo of several attached buildings in preparation for additions to historic building.
Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers February 24th, 2020 to March 1st, 2020.
Design Advice has been requested by Hennebery Eddy Architects for a project at 539 NW 10th Ave:
Project consisting of a new +/-11-story hotel with partial basement on a quarter-block site. The new structure will replace an existing 1-story commercial building. The hotel will contain 150-160 guest rooms with 85,000-90,000 square feet. Loading access is planned along NW Hoyt Street, with a single interior loading bay. No off-street parking is proposed. Ground floor program includes hotel lobby, restaurant, lounge, kitchen, offices, restrooms, mechanical rooms and bike storage. Floors 2-11 will be primarily guest rooms with limited amenity spaces such as fitness room, board room and a roof terrace with bar. Stormwater treatment and detention will be accomplished by way of a vegetated roof.
Design Advice has been requested by SERA Architects for a project at 2250 NW Flanders St:
6-story apartment building with approximately186 units in the Northwest Plan District and Alphabet Historic District. Stormwater disposal method TBD.
Design Advice has been requested by SERA Architects for Conway Block 291 East at the SW corner of NW 20th & Raleigh:
7 story market rate apartment building with 180 residential units and basement parking. Stormwater disposal will occur through drywells in the pedestrian way.
A Pre-Application Conference has been scheduled by SERA Architects to discuss a project at 306 SE 8th Ave:
New 7 story market-rate apartment building with 113 units and ground floor retail.
Cathedral Village at 8614 N Crawford Street has been submitted for a Pre-Permit Plan Check by MWA Architects:
4-story apartment building with 110 affordable family apartments. The unit mix will be (11) 3-bedrooms, (45) 2-bedrooms, (37) 1-bedrooms, and (17) studios. There will be resident services on the ground floor and 37 parking spaces. There is a basement level at the NW corner of the building that will house bike parking and storage.
A project at 4039, 4047 and 4051 N Williams Ave has been submitted for Type II Design Review by William Kaven Architecture:
Construction of two new 4-story buildings organized around a shared courtyard.
Two new four-story buildings located on N Williams Ave, mid-block between N Mason St and N Shaver St.
New four-story commercial (office) comprised of three stories of office over ground floor retail, office, lobby and tuck-under parking.
A project at 1137 NW 23rd Ave has been submitted for Type III Design Review by GBD Architects:
New mixed use building with ground level retail, 4 levels of apartments above, and 1 level of below grade parking. 74 units.
The new building adjacent to the Troy Laundry at 1010 SE Ash St has been submitted for a Type III Historic Resource Review by Hartshorne Plunkard Architecture:
New 6-story multi-family residential project with two below-grade parking levels.
A project at 236 SE Grand Ave has been submitted for Type III Historic Resource Review by TVA Architects:
New 8-story, 130,000 sq ft office building. One adjustment requested to the loading stall.
The Benson Polytechnic High School Modernization has been submitted for Type III Historic Resource Review by Architectural Resources Group:
Modernization of the existing Benson Polytechnic High School (BPHS) building.
A project at 11 NE 55th Ave has been submitted for building permit review by Fosler Portland Architecture:
Construct new 3 story 16 unit apartment building with associated site work
A project at 5905 N Interstate Ave has been submitted for building permit review by Studio 3 Architecture:
New 3 story, 19 units apartment building with partial retail on ground floor and associated siteworks. Trash enclosure inside.
A project at 8157 N Lombard St has been submitted for building permit review by Mackenzie:
Construction of a 3-story, 8,375 sf multi-family building with eleven (11) units. Ten (10) of these units will be 550 sf and one (1) will be 813 sf.
A project at 6307 N Montana Ave has been submitted for building permit review by Fosler Portland Architecture:
Construct new 3 story 19 unit apartment building with associated site work
A project at 503 SE 29th Ave has been submitted for building permit review:
New 4 story 30 unit apartment building
A project at 6962 N Maryland Ave has been submitted for building permit review:
New 4-story 12-unit apartment with associated site work; w/20-124476-MT
A project at 2148 NE Martin Luther King Jr Blvd has been submitted for building permit review by Ankrom Moisan Architects:
New two-story, 27,595 square foot brick office building with an adjacent surface parking area for ten vehicles