Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers January 4th, 2021 to January 10th, 2021.
Early Assistance has been requested by Holst Architecture for a project at 5542 NE Killingsworth St:
REVIEW UNDER CURRENT CODE: Residential infill affordable housing development with approximately (63) units with associated on-site parking and site improvements. Stormwater will be managed on site in accordance with BES standards.
Early Assistance has been requested by Holst Architecture for a project West of 4729 SW Taylors Ferry Rd:
REVIEW UNDER CURRENT CODE: Residential infill affordable housing development with approximately (22) units with associated on-site parking and site improvements. Stormwater will be managed on site in accordance with BES standards.
A building permit was issued to Doug Circosta Architect for a project at 1675 NE 41st Ave:
PDOX PS – new 5 story 17 unit apartment building with associated site work; site work to include common area and detached trash enclosure < 120 sf ***mechanical permit to be separate***
Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers June 1st, 2020 to June 7th, 2020.
Early Assistance has been requested by Studio 3 Architecture for a project at 4738 SE Belmont St:
New 3-Story, mixed-use structure. 19 apartment units are proposed. The ground floor will contain 1,150 sf of commercial lease space along Belmont St. The project total square footage is 11,473. A drywell on the south end of the site will serve to dispose of stormwater. They plan to meet community design standards.
Early Assistance has been requested by Marathon Acquisition And Development for a project at 2202 E Burnside St:
New 5-story, mixed-use building. Approximately 114 units, 115,800 SF. Stormwater management is TBD. Proposal is expected to meet community design standards, however, applicant would like update/info about DOZA implementation.
Early Assistance has been requested by SERA Architects and Home Forward for The Baldwin Affordable Housing at 7688 N Interstate Ave:
Develop a 4-story low-income apartment building with ground floor permanent supportive service offices, community room, and courtyards. Stormwater disposal method is pending results from geotech report.
A Pre-Application Conference has been scheduled by Barghausen Consulting Engineers to discuss a project at 1525 SE Grand Ave:
A Pre-Application Conference to discuss construction of a 12,450 square foot retail building (CVS Pharmacy). A drvie through window and a surface parking lot for 30 vehicles is proposed. There are curb cuts on both SE M L King and SE Grand for the parking lot and the drive-through. The drive-through exits onto SE Clay Street. An Early Assistance meeting was held in 2019 to discuss this project (19-238518)
A project at 1675 NE 41st Ave has been submitted for building permit review by Doug Circosta Architect:
PDOX PS – new 5 story 17 unit apartment building with associated site work; site work to include common area and detached trash enclosure < 120 sf ***mechanical permit to be separate***
The Large Division Apartments at 11518 SE Division St has been submitted for building permit review:
LARGE DIVISION – New 4-story building with 138 affordable housing units, support services, and surface parking; includes associated site work *** w/20-145394-CO, 20-145396-CO, and 20-145399-MT ***
The Kōz on N Killingsworth 2 at 1430 N Killingsworth St has been submitted for building permit review:
New 6 story, 154 unit apartment building with ground floor retail and associated site work. W/20-146522-MT
A foundation only permit for the Press Blocks Full Block has been submitted for building permit review:
Building Foundation Only for new 24 story multi-family tower & 4 story plaza office building
A building permit was issued to LRS Architects for an addition to the Gateway Baptist Church at 13300 NE San Rafael St:
Two story addition to west side of existing worship hall. Includes demo of stair, lobby, restrooms, exterior ramp on west side and siteworks to add new elevator, accessible restrooms and stair and siteworks.
Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers November 11th to November 17th, 2019.
Early Assistance has been requested by Hacker for a project at 1709 SE 3rd Ave:
New creative office development to be developed in 2 phases, as two distinct buildings. “Phase 3” is the renovation of an existing bow-string truss warehouse with basement level parking. “Phase 4” is a 6+ story mass timber office building over two levels of underground parking. This EA is to discuss the land division.
Early Assistance has been requested by Doug Circosta Architect for a project at 1675 NE 41st Ave:
Build a new community building of 16 independent residences that provide mutual support, shared services, personal autonomy, security and ease of maintenance. There will be shared spaces for gathering, fitness, therapy, creation of art, enjoyment of art, meal prep and family-style dining.There will also be an on-site space for creative work: art therapy studio, music therapy studio, and display/gallery spaces.
Early Assistance has been requested by Quilici Architecture & Design for a renovation to the New Market Theater at 120 SW Ankeny St:
This project involves the renovation of retail spaces in ‘greenhouse’ structure of the New Market Theater. Options A, B and C are under consideration. Option A is least intensive and Option C the most. The project may include the reduction or elimination of existing parking, an increase of the retail area, and modifications to the exterior.
Early Assistance has been requested by Studio 3 Architecture for a project at 5905 N Interstate Ave:
New 3-story, mixed use structure. 19 apartments units are proposed. the ground floor will contain 959 sf of commercial lease space along Interstate Ave. The project total square footage is 12,216. a drywell on the north end of the site will serve to dispose of stormwater.
Early Assistance has been requested by Lenity Architecture for a project at 3015 SE Berkeley Pl:
Construction of an approximately 150-suite retirement residence and other senior-related uses.
Early Assistance has been requested by Zody Architecture for a project at 10340 SE Division St:
The concept of this project is to construct a new assisted living and memory care community to serve the local residents of the community. the project is currently envisioned to house between 90-120 residents. An existing medical office building will be replaced as part of the project and two residential homes will be demolished. The current concept design houses memory care on the first floor and assisted living on two upper floors. A basement level will provide support services.
A Pre-Application Conference has been scheduled by SERA Architects to discuss a project for the Northwest Children’s Theater at 2135 NW 29th Ave:
Performance and education facility for Northwest Children’s Theater. One level of partially-below-grade parking; two levels of performance, edcuation, and administrative space above. Combination of stormwater planters and eco-roof being considered; assume no infiltration allowed due to fill.
A Pre-Application Conference has been scheduled by SERA Architects to discuss a project at Con-way Block 292 East at the southwest corner of NW Savier & 20th:
6 story market rate senior apartment building with 186 residential units and basement parking. Stormwater disposal will occur through drywells in the pedestrian way.
Buildings permits are under review for buildings on the University of Portland Franz Campus (also known as the River Campus) at5828 N Van Houten Pl:
Track & Field complex including a 523 seat covered Grandstand (Part C on Plans): Construction of a new Collegiate Track & Field Facility including 6 lighting poles. See Comments
New single story, slab on grade, 46,682 sf physical plant with related mechanical, plumbing, electrical, and site work. Type II B Non-combustible construction, fully fire sprinklered. Separate PT and ET required. See Comments
New 12,880 sf Boathouse and Environmental Lab building w/ 2,389 sf mezzanine. Work includes utility infrastructure, stormwater facilities, grading, paving, sitework & site lighting, and Greenway trail. See Comments
A building permit was issued for a project at 4415 SE 61st Ave:
New 3 story, 9 unit apartment building with associated site work, and attached trash enclosure with recycle area; short term bike racks; no onsite parking