Starting October 2021, Metro Reports have moved to Portland Maps Reports. Next Portland covers the highlights of the Early Assistance applications, Land Use Reviews and Building Permits processed each week. This post covers November 1st, 2021 to November 7th, 2021.
Early Assistance has been requested by Base Design and Architecture for a project at 957 NE 122nd Ave:
Applicant is proposing a lot division of the existing parcel and generation of two new parcels. A 13,895 SF parcel for a new 11,738 SF (18) unit development and a 66,369 SF parcel that contains the existing 40,464 SF apartment complex and parking lots. The western parcel will be accessed from NE Holladay and have (9) new parking stalls and provide a 20′ access easement to the eastern parcel for it to access its remaining parking stalls.
Early Assistance has been requested by Works Progress Architecture for a project at 2631 NW Upshur St:
New Development Of 109 Residential Units. 57 Residential Parking Spaces, Ingress From & Egress To Nw Vaughn, Ingress Only From Nw Upshur. On Site Loading. Storm-Water To Be Managed On-Site.
Early Assistance has been requested by McGuirl Designs & Architecture for a project at 1340 SE 12th Ave:
New 5 Story, 113 Unit Multi-Family Building. 2 Loading Zones Provided. 170 Bike Parking Spaces Required, 85 Provided In Unit And 93 On Ground Floor. Common Outdoor Area Requirement Met With Outdoor Courtyard On Ground Level And Roof Deck. Stormwater Managed With On-Site Drywell.
Traditions At Hazelwood at 10451 E Burnside St has been submitted for building permit review by Inland Group:
Traditions At Hazelwood – New 211 Unit Six Story (5 Over 1) Affordable Housing Apartment Building With One Level Of Underground Parking For Approximately 69 Vehicles In The Gateway District. **Review W. 21-102767-Mt. Demo’S Of Existing Structures Under Separate Permits
A project at 1375 N Killingsworth St has been submitted for building permit review by Fosler Portland Architecture:
Pdox Ps – 5-Story, 69-Unit Apartment Building With Indoor Bike Room, Trash Area, Vehicle Loading/Unloading, 6 Live-Work Spaces, Rooftop Deck, And Associated Site Work. W/ 21-096336-Co For Outdoor Bike Corral.
A building permit was issued for a project at 5042 NE Fremont St:
Pdox Ps – New 3 Story 10 Unit Apartment Building With Ground Floor Retail And Associated Site Work W/20-161390-Mt
Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers August 2nd, 2021 to August 8th, 2021.
Design Advice has been requested by McGuirl Designs & Architecture for the Market Street Apartments at 1541 SW Market St:
New affordable housing, multi-family building. 8 stories. 125 dwelling units. 2 Off-street loading zones. Stormwater disposal utilizing flow through planters.
A project at 5802 SE 92nd Ave has been submitted for a Pre-Permit Plan Check by Otak:
The proposed project is a multifamily residential building with 47 units and a commercial space in a 5-story building. The building will be connected to an existing 3-story building on the same site. Storm water for the existing building will remain as-is and the new portion of the building will handle storm water via an on-site drywell. No on-site parking will be provided.
A project at 6116 NE Willow St has been submitted for a Pre-Permit Plan Check:
New 9 unit apartment
A project at 10413 E Burnside St has been submitted for a Type II Design Review by Inland Oregon:
We are proposing to build a 211 unit six story (5 wood over 1 concrete) apartment building with one level of underground parking. Units will be restricted to households earning no more than 60% AMI.
A project at 605 SE Spokane St has been submitted for building permit review by Studio Cropp:
Single PDF – construct new 3-story, 8 unit residential complex. 4 units are 2-story and 4 units are single story on ground floor with associated site work.
A project at 2510 SE 21st Ave has been submitted for building permit review by Allusa Architecture:
Single PDF – construct new 2-story restaurant.
The PCC Metropolitan Workforce Training Center at 5600 NE 42nd Ave has been submitted for building permit review:
New two-story, approximately 50,000 sf office building and training center with a mass timber structural system. Includes classrooms, conference and meeting rooms, career center, open office spaces, common areas, a community room, and a leased partner space (w/21-106109-MT). Trash/recycling area included (21-056112-CO).
Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers May 17th, 2021 to May 23rd, 2021.
Design Advice has been requested for a project at 10413 E Burnside St:
Construction of a 211-unit six story (5 wood over 1 concrete) apartment building with one level of underground parking. Units will be restricted to households earning no more than 60% AMI.
Design Advice has been requested by SERA Architects for Con-Way Blocks 261 and 262:
The proposal is for blocks 261 and 262 in the Con-Way Master plan area. The proposed development will be market rate apartments on both parcels. Block 261 will be a 5 story building with tuck under parking, and block 262 will be a 6 and 7 story building with basement parking. Stormwater disposal is anticipated to be through dry wells
Early Assistance has been requested by Holst Architecture for a project at 432 NE 74th Ave:
RIP Code Analysis – Multi-family affordable housing development with approximately 125 units with associated on-site parking and site improvements on a split-zone (CM2 & R2.5) site. Stormwater will be managed on site in accordance w/ BES standards.
Early Assistance has been requested by Works Progress Architecture for a project at 4520 N Colonial Ave:
Development of a three story multi-family apartment building. Site will provide bike parking, on site parking, and has designated easements for fire access and pedestrian access to the adjacent site.
Early Assistance has been requested by Works Progress Architecture for a project at 1560 N Going St:
Development of a three story multi-family apartment building. Site will provide bike parking, and has designated access for fire and pedestrians by easements through the adjacent site.
Early Assistance has been requested by Scott Edwards Architecture for a project at 3314 SE Powell Blvd:
The project team is looking at two new commercial development options, with Option B, being chosen as the option for discussion. Option A: The proposed scope of work includes the design and construction of a new one-story, 5,000 SF commercial building. Option B: The proposed scope of work includes the design and construction of a new 3-story, 28,000 SF core and shell building for commercial use.
A Pre-Application Conference has been scheduled by GBD Architecture to discuss the RiverPlace Redevelopment:
A Pre-Application Conference to discuss a proposed Central City Master Plan for approximately 8 acres that includes the following addresses: 0150, 0308 – 0320 SW Montgomery St., and 2025 WI/ and 2025 SW River Parkway.
The ALTA Centric at 1634 SW Alder St has been submitted for building permit review by SERA Architects:
ALTA CENTRIC – New mixed-use multifamily project with 6 residential stories, 203 apartment units with common areas for bike parking, lobby/mail, and a future retail tenant (by others). Concrete on levels P1 and L1 with wood-framed construction above. ***Review w DEMO 21-049475-CO and 20-135132 -MT
The Isaka Shamsud-Din Apartments at 5421 NE 14th Pl have been submitted for building permit review:
New Four story, 29 unit affordable multi-family residential complex located on NE 14th Place at NE Killingsworth. No parking to be provided. Community room and shared outdoor space to be provided. Proposed site development includes new utilities, accessible courtyard, landscaped areas and street trees. (with 21-036139-MT)
A project at 5740 NE 72nd Ave has been submitted for building permit review:
East Building / New three story, 6 unit multi-family building consisting entirely of affordable housing composed of two building. Surface parking to be provided. Community room and shared outdoor space to be provided. Proposed site development includes new utilities, landscaped areas and parking. (w/ 21- 036221-MT)
West Building / New three story, 6 unit multi-family building consisting entirely of affordable housing composed of two building. Surface parking to be provided. Community room and shared outdoor space to be provided. Proposed site development includes new utilities, landscaped areas and parking. (w/ 21- 037910-MT and 21-036216-CO & 21-036221-MT).
A building permit was issued for a project at 2475 SE 30th Ave (previously 2933 SE Division St):
Construct new 4 story mixed use building; main floor to include retail space and 2 residential units; floor 2-4 to include 16 apartment units; associated site work
Building permits were issued to Doug Circosta Architect for the 146th & Burnside East Apartments at 10, 20 and 30 NE 146th Ave (previously 14603 E Burnside St):
146 EAST – BLDG 100 – This project consists of 70 total new affordable apartment units. The units are located in (3) detached three story buildings with on- site parking spaces, user amenities, and trash enclosure. Unit counts are 30 in Building 100, 24 in Building 300, and 16 in Building 200. Both the bike shelter and trash enclose will require separate permits. ** No Mechanical with these permits *****review w. 20-173847/51/72-CO
146 EAST – BLDG 200 – This project consists of 70 total new affordable apartment units. The units are located in (3) detached three story buildings with on- site parking spaces, user amenities, and bike parking inside trash enclosure. Unit counts are 30 in Building 100, 24 in Building 300, and 16 in Building 200. Both the bike shelter and trash enclose will require separate permits.**No Mechanical with these permits****review w. 20-173775/851/872-CO
146 EAST – BLDG 300 – This project consists of 70 total new affordable apartment units. The units are located in (3) detached three story buildings. Bike parking in trash enclosure. Unit counts are 30 in Building 100, 24 in Building 300, and 16 in Building 200. Both the bike shelter and trash enclose will require separate permits.***review w. 20-173775/847/872-CO
Building permits were issued to Doug Circosta Architect for the 146th & Burnside West Apartments at 11 and 21 NE 146th Ave (previously 14507 E Burnside St):
146 WEST – New 3-story, 24 Unit apartment building (1 of 2) with detached trash enclosure and associated site work. No Mechanical with this permit ***Review with 19-256079-CO (BLDG 2) and 19-256081-CO (Trash Encl) ***Transitioned to Complex ProjectDox Review 12/29/20
146 WEST Bldg B200 – new 3-story 22 unit apartment building with office and common laundry room. No Mechanical with this permit **Review w. 19-256078- CO & 19-256081-CO. *** Project transitioned to “complex” plan review and Process Managed after 1st review cycle.
A building permit was issued for Floor & Decor at 11941 N Jantzen Dr:
PDOX PS – new 1-story building for flooring retailer with associated sitework w/20-203128-MT
Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights. This post covers March 1st, 2021 to March 7th, 2021.
Early Assistance has been requested by Jones Architecture for a project East of 208 NE Hancock St:
New 3-story, 18-unit multi-family, micro-unit residential building. Stormwater management TBD
Early Assistance has been requested by TriMet to discuss the HollywoodHUB at 4110 NE Halsey St (current Hollywood Transit Center):
Vacation of NE 42nd Avenue between NE Halsey Street and I-84 Pedestrian Bridge to allow for (i) the construction of new pedestrian/bike access to the Hollywood MAX Station and Laurelhurst neighborhood, (ii) new TriMet and public infrastructure, and (iii) to make the Hollywood Transit Center viable for a new 213-unit affordable housing building. Stormwater treatment will be in dry wells on site with additional bio swales as needed. Detailed project information is included in the attached presentation.
A Pre-Application Conference has been scheduled to discuss a project at 10413 E Burnside St:
We are proposing to build a 225 unit six story (5 wood over 1 concrete) apartment building with one level of underground parking. Units will be restricted to households earning no more than 60% AMI. We are evaluating site conditions for infiltration, if not feasible we will discharge to the public storm system.
A project at 234 NE 61st Ave has been submitted for building permit review:
PDOX PS – Construct new 3 story 15 unit apartment building with associated site work
Freewell at 2030 NW Raleigh St has been submitted for building permit review by SERA Architects:
FREEWELL – BLOCK 291E – New 7-story apartment building with 192 apartment units, residential amenity spaces, and commercial space attached to new 2-story pavilion building by 2nd level pedestrian bridge; includes one level shared below grade parking and associated site work *** w/20-203695-MT ***
Building permits were issued to Studio 3 Architecture for a project with buildings at 5960 and 5980 E Burnside St:
New 4-story 42-unit apartment building with associated site work; no onsite parking; detached trash enclosure < 120 sf; mechanical permit separate for w/19-269743/44-CO
New 4-story 29-unit apartment building with associated site work; no onsite parking; detached trash enclosure < 120 sf; mechanical permit separate for /19-269743/44-CO
A building permit was issued to Stewart Gordon Straus Architect for a project at 278 SW Arthur St:
New 2 story office building, parking lot, site improvements, landscaping, retaining walls.(mechanical separate)