Weekly Roundup: Goat Blocks, Hi-Lo Hotel, Karl Miller Center, and more

Businesses have started to open in the Goat Blocks development

Eugene-based grocery store Market of Choice opened last week in the Goat BlocksThe Portland Business Journal published photos of the new grocery store and the adjacent Orchard Supply Hardware. Schilling Cider, which plans the “world’s largest cider taproom” has set an opening date of June 16th.  

Eater PDX took a look at Alto Bajo, the modern Mexican restaurant opening tomorrow in the Hi-Lo Hotel.

Residents of Multnomah Village are challenging Portland’s recently passed Comprehensive Plan, writes the Portland Tribune.

The DJC wrote about how the project team behind the PSU Karl Miller Center is zeroing in on a LEED platinum rating*.

The Portland Tribune wrote about the current state of the construction market in Portland, with hotel development being particularly strong.

*This article will be unlocked for the rest of this week. After this week it will only be viewable by DJC subscribers.

Hoodworks Approved by Design Commission (images)

The Design Commission has approved a Hoodworks, a proposed office building in South Portland. The four story building by Koble Creative Architecture for Summit Development Group and Point B Development will be framed out of Cross-Laminated Timber. The 16,900 sq ft buiding will include retail/office space at the ground floor. 9 vehicular parking spaces and 7 bike parking spaces will be provided in a tuck-under parking area.

Hoodworks

Read More

Block 290 & Slabtown Square Reviewed by Design Commission (images)

An initial design review hearing has been held for the Block 290 development at NW 21st and Pettygrove. The project by LRS Architects and PLACE Studio for Guardian Real Estate Services will include a new publicly accessible square, surrounded by a mixed use building of four to seven stories in height. The project will will include 201 residential units over ground floor retail. 107 vehicular parking spaces are proposed in a below grade garage.

Conway Block 290

Read More

Metro Reports: 3403 N Mississippi, NE 106th & Halsey, Neuberger Hall, and more

Construction has started on a project by Holst Architecture at 3403 N Mississippi Ave

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights.

Design Advice has been requested by DLR Group for a project at 539 SW 10th Ave:

Construct a new hotel with approximately 177 rooms, 11 stories. (Central City, Downtown, West End Plan District – Central City Design District)

Early Assistance has been requested by Holst Architecture for a project at NE 106th & Halsey:

Proposal is for a six story building with 45 affordable housing units, 30 market rate apartments, tuck-under parking, 10,000SF of retail and 10,700SF of office space. Amenities to include community room and green roof deck.

A Pre-Application Conference has been scheduled by Mainland Northwest to discuss a project at West of 8524 N Crawford St:

Previous EA 15-219376. Proposal to change the zoning, consistent with the Comprehensive Plan Map designation, from EG1 (General Employment 1) and EG2 (General Employment 2) to EXd (Central Employment zone with the Design overlay zone). The applicant states the future development on this 15-acre site could include multi-dwelling residential, neighborhood retail, mixed office-manufacturing uses. The greenway trail will also be developed. This application does not include a specific development plan.

The PSU Neuberger Hall Renovation has been submitted for Type III Design Review by Hacker architects:

Renovation of PSU’s Neuberger Hall, which includes updates and modifications to accessibility, fire and life safety, upgrades to MEP systems, seismic strengthening, program adjustments and facade improvements. One modification requested to Ground Floor Windows (33.130.230, 33.510.220)

The renovations to the Meier & Frank Building have been submitted for Type III Design Review by Bora Architects:

Project is located at former Macy’s department store. Floors 1-5 and basement to be demolished and renovated as creative office space with ground level retail. New restrooms will be added to the office floors to accommodate future office tenant improvement. Basement amenity space including bike storage, fitness and conference space will be provided.Scope includes limited facade renovations to accommodate restored retail entries mid block on SW 5th and SW 6th and a new entry on SW 6th near Morrison. Each entry will include a new canopy. The SW Alder canopy will be reduced in depth per PBOT requirements. The historic facade and SW Morrison canopies will be preserved.

A building permit was issued to Holst Architecture for a project at 3403 N Mississippi Ave:

Excavation and Shoring

A building permit was issued for a project at 5025 N Minnesota Ave:

New 6 unit apartment building with associated site work

Weekly Roundup: Hawthorne 31, Hi-Lo Hotel, High Schools, and more

The Hi-Lo Hotel, located in the Oregon Pioneer Building, is set to open at the end of the month. The building is also home to iconic Portland restaurant Huber’s.

Portland voters approved the $790 million Portland Public Schools bond, which will pay for the rebuild or modernization of Benson High SchoolMadison High SchoolLincoln High School and Kellogg Middle School.

At three and a half months into Portland’s Inclusionary Housing program, the Business Tribune looked at the policy’s success so far.

SE Hawthorne now has a second poke bowl restaurant, at the ground floor of the Hawthorne.31 Apartments, writes Eater PDX.

Demolition began on the former Club 21 building, reported the Portland Mercury. The site is being redeveloped as the Jantzen Apartments.

Portland Monthly looked at the Field Office, a “radical new Portland office [that] blends work and nature“.

The Hi-Lo Hotel and Alto Bajo restaurant will open May 31st, according to Eater PDX.

Hammer & Hand Office and Workshop approved by Landmarks Commission (images)

A new office and workshop for construction company Hammer & Hand has been approved by the Historic Landmarks Commission. The two story building by Holst Architecture will include workshop space at the ground level, with office space and a roof deck above. The project is being designed to meet Passive House standards, with the intention that the office portion of the building will achieve net zero energy use. No vehicular parking is proposed.

Hammer & Hand Office and Workshop

Read More

Metro Reports: 3rd & Taylor, Jantzen Apartments, 4040 SE Division, and more

3rd and Taylor

A building permit is under review for the 3rd & Taylor office building

Every week, the Bureau of Development Services publishes lists of Early Assistance applications, Land Use Reviews and Building Permits processed in the previous week. We publish the highlights.

Early Assistance has been requested by Quilici Architecture & Design Inc for a project at 4040 SE Division St:

Proposal is for a new 38 units with affordable housing (20,640 sf total) without parking. Stormwater planter provided along south PL. Main enterance and lobby on Division St. Trash and recycle room located on north side of building and accesed off Difision St. Existing commercial structure and all trees on-site to be removed.

Early Assistance has been requested by Quilici Architecture & Design Inc for a project at 3212 SE Division St:

Proposal is for a 32 unit apartment complex which includes affordable housing (20,640 sf total) without parking. Stormwater planter provided along south PL. Main enterance and lobby on 32nd Avenue. Trash and recycle room located on south side of building and accessed off 32nd. Existing commercial structure and all trees on-site to be removed.

A building permit application has been submitted for review by David Rodeback Architect for alterations to an existing building at 6012 SE Yamhill St:

Existing 4-story building – change of occupancy and use from R1, B, |A3 to R2 & A3 with 62 new apartment units and 14 sleeping units added, and complete seismic retro fit for entire building

A building permit application has been submitted for review by SERA Architects for the Jantzen Apartments at 518 NE 20th Ave:

New 6 story above grade with full basement. 211 apartments, 114 parking stalls, with retail, common space on ground floor

A building permit application has been submitted for review by TVA Architect for a project at 5036 NE Sandy Blvd:

New 6-story, 85 unit apartment building; ground floor shell only; recycle room; with onsite parking, includes associated site work***with 17-169667-MT permit***

A building permit application has been submitted for review for a project at 5419 SE Woodstock Blvd:

New 3 story 38 unit apartment building; interior trash enclosure; associated site work

A building permit application has been submitted for review by Ankrom Moisan Architects for the 3rd & Taylor office building:

New 10 story speculative office building, ground floor retail and comond and support area serving office functions, 2 stories of below grade parking

A building permit was issued for a project at 1211 SE Morrison St (previously 1205 SE Morrison St):

Construct new 4 story (39) unit apartment building with parking and bike storage on main level; associated site work

PSU Neuberger Hall Renovation receives Design Advice (images)

A major renovation of Portland State University’s Neuberger Hall has gone before the Design Commission to receive Design Advice. The project is being designed by Hacker architects, and includes a complete interior renovation designed to address significant deferred maintenance. Significant alterations will also be made to the exterior envelope of the building, much of which is currently failing.

PSU Neuberger Hall

Read More

Weekly Roundup: Porter Hotel, Towne Storage Building, Providence Park, and more

Construction is well underway on the Porter Hotel in Downtown

The Portland Chronicle wrote about the demolition of a 1930 funeral home. The site at 80 NE 14th Ave is being redeveloped as a six-story mixed-use building containing 190 residential units.

Eater PDX reported that Touché Restaurant was set to close this Sunday after 20 years in the Pearl. The historic firehouse that housed the restaurant will be renovated as part of the Modera Glisan development.

The Portland Business Journal reported that software company Autodesk will move 200 employees from Lake Oswego to the Towne Storage Building in the Central Eastside.

The DJC wrote about the massive number of new hotel rooms coming online, including at the AC Hotel, Convention Center Hotel, The Woodlark and The Porter.  If all hotel projects currently proposed get built they “would expand Central Portland’s room count by 35 percent by 2020.”*

The Oregonian reported that the Portland Timbers’ proposed expansion of Providence Park drew City Council support at a hearing held last week.

As Esco Corp. winds down operations in NW Portland The Oregonian reported that its 15 acre site is being prepared for redevelopment.

Portland for Everyone wrote about the eleven bills aimed at tackling housing prices that are still alive in the legislature.

*This article will be unlocked for the rest of this week. After this week it will only be viewable by DJC subscribers.